Bezzi Posted February 11, 2013 Author Report Share Posted February 11, 2013 The numbers: BEL |..................Ready| FOR |..................Ready| SAL |...................95%.| REC |..................90%..| BRA |..................89%..| RIO |................80%....|* SAO |.............64%.......| CUI |............62%........| POR |............58%........| CUR |...........56%.........| MAN |..........52%..........| NAT |..........50%..........| * This number is from november. The consortium has not updated the information since then. By the progress, the stadium surely surpassed 90%. Link to comment Share on other sites More sharing options...
gotosy Posted February 22, 2013 Report Share Posted February 22, 2013 h An aerial view shows the roof installation at the Maracana Stadium, which is undergoing renovation for the 2014 World Cup, in Rio de Janeiro February 22, 2013. The stadium will also host games for the 2013 Confederations Cup and the Rio 2016 Olympic Games. REUTERS/Ricardo Moraes Link to comment Share on other sites More sharing options...
DannyelBrazil Posted February 28, 2013 Report Share Posted February 28, 2013 Updates!!! Link to comment Share on other sites More sharing options...
DannyelBrazil Posted February 28, 2013 Report Share Posted February 28, 2013 FORTALEZA Arena Castelão FINISHED BELO HORIZONTE Mineirão Stadium FINISHED SALVADOR Arena Fonte Nova RIO DE JANEIRO Maracanã Stadium BRASÍLIA Estádio Nacional RECIFE Cidade da Copa SÃO PAULO Arena de São Paulo CURITIBA Arena da Baixada PORTO ALEGRE Beira Rio Stadium NATAL Arena das Dunas MANAUS Arena da Amazônia CUIABÁ Arena Pantanal Link to comment Share on other sites More sharing options...
Bezzi Posted March 1, 2013 Author Report Share Posted March 1, 2013 Update: BEL |..................Ready| FOR |..................Ready| SAL |....................99%| REC |...................95%.| BRA |..................92%..| RIO |..................87%..| SAO |.............65%.......| CUI |............62%........| POR |............58%........| NAT |...........57%.........| CUR |...........56%.........| MAN |...........54%.........| Salvador allmost ready! Link to comment Share on other sites More sharing options...
WorldCupJoe Posted March 1, 2013 Report Share Posted March 1, 2013 Thanks for the updates! Salvador is becoming my favorite more and more. Great stadium with a cool roof structure and the color of the seats makes it look really fresh. Link to comment Share on other sites More sharing options...
deawebo Posted March 2, 2013 Report Share Posted March 2, 2013 Stadiums looking great!! Brasilia is still looking the best of all venues, Salvador great too. Link to comment Share on other sites More sharing options...
Olympian2004 Posted March 7, 2013 Report Share Posted March 7, 2013 The famous "águas de março" of Rio de Janeiro take their toll at Maracanã - and the stadium's construction progress causes the "biggest worry" for FIFA general-secretary Jérôme Valcke: NBC Sports: FIFA Visit to Maracana canceled because of floods Hmmm... so this is apparently becoming a nailbiter like the construction of the refurbished Athens Olympic Stadium in 2004. But in the end, they managed to finish that in time, too. Link to comment Share on other sites More sharing options...
WorldCupJoe Posted March 7, 2013 Report Share Posted March 7, 2013 Time to follow this project more closely. Interesting. They will finish it on time, no doubt about it. But they really have to speed up. Always nice to have a little drama during the build-up to a tournament. Good thing they've prevented a third strike (or fourth or fifth, how much is it?) Time to rewrite and add some things do this article: http://www.worldcupofjoe.com/1/post/2013/01/the-maracan-way.html Link to comment Share on other sites More sharing options...
Bezzi Posted March 8, 2013 Author Report Share Posted March 8, 2013 Your site is cool. But some things are not updated, as the picture of Fortaleza stadium, which have already been completed and also the stadium capacities. I think you should also update the information about the Maracana. The government of Rio said yesterday that the stadium will be completed next month, despite the problem with the rain. The date of May 28 is when "ALL" the CC stadiums shall be delivered to the FIFA administration. The press here was mistaken stating that the stadium would be ready only in May. Link to comment Share on other sites More sharing options...
intoronto Posted March 8, 2013 Report Share Posted March 8, 2013 Salvador's stadium = perfect Link to comment Share on other sites More sharing options...
DannyelBrazil Posted March 8, 2013 Report Share Posted March 8, 2013 The famous "águas de março" of Rio de Janeiro take their toll at Maracanã - and the stadium's construction progress causes the "biggest worry" for FIFA general-secretary Jérôme Valcke: NBC Sports: FIFA Visit to Maracana canceled because of floods Hmmm... so this is apparently becoming a nailbiter like the construction of the refurbished Athens Olympic Stadium in 2004. But in the end, they managed to finish that in time, too. No single line about the billion-dollar works to avoid floodings in the Maracana area, to be inaugurated in november. Two underground rivers will get detours and a underground "pool" is under final works to store the flooded waters... Maybe one of the biggest legacies of the World Cup in Rio, but this is not interesting to publish in the Int'l media... Link to comment Share on other sites More sharing options...
DannyelBrazil Posted March 8, 2013 Report Share Posted March 8, 2013 Pictures of the works to solve floodings near Praça da Bandeira area The pictures were taken by Brazilian forumers of SSC after the flodding in Maracana just to prove works have been done to solve this problem definitvely. That's why the look of the pictures are a mess of mood. This is not the actual like of the works around Maracana, as you can see in these pics from a week ago: Link to comment Share on other sites More sharing options...
Bezzi Posted March 9, 2013 Author Report Share Posted March 9, 2013 Salvador handed the third stadium for the 2014 World Cup! The first match of the Fonte Nova will be played on April 7: http://globoesporte.globo.com/ba/noticia/2013/03/fonte-nova-e-entregue-ao-governo-e-imprensa-conhece-espacos-internos.html Soon I'll post more pictures Link to comment Share on other sites More sharing options...
WorldCupJoe Posted March 9, 2013 Report Share Posted March 9, 2013 Whohoo! 3 out of 12 stadiums completed. Congrats to Salvador. Are they going to build the temporary stand in the empty space for the confederations cup too, or just for the world cup? Link to comment Share on other sites More sharing options...
Bezzi Posted March 9, 2013 Author Report Share Posted March 9, 2013 BEL |...................100%| FOR |...................100%| SAL |...................100%| REC |...................95%.| BRA |..................92%..| RIO |..................87%..| SAO |.............66%.......| CUI |............62%........| POR |............62%........| NAT |...........57%.........| CUR |...........56%.........| MAN |...........54%.........| Link to comment Share on other sites More sharing options...
Bezzi Posted March 9, 2013 Author Report Share Posted March 9, 2013 Whohoo! 3 out of 12 stadiums completed. Congrats to Salvador. Are they going to build the temporary stand in the empty space for the confederations cup too, or just for the world cup? The installation of temporary seats will begin on march 18 and will be ready for te confederations cup. Link to comment Share on other sites More sharing options...
tomjsteer Posted March 10, 2013 Report Share Posted March 10, 2013 Salvador looks amazing! Does anyone know if the temporary seats will just be one tier? How far will it increase the capacity? Link to comment Share on other sites More sharing options...
intoronto Posted March 10, 2013 Report Share Posted March 10, 2013 What happened ?? There is a huge gap in Salvador's stadium Link to comment Share on other sites More sharing options...
Bezzi Posted March 10, 2013 Author Report Share Posted March 10, 2013 ^^^^ It's the place where they will install 5000 temporary seats. I think they will close 2 of the 3 tiers. Link to comment Share on other sites More sharing options...
Bezzi Posted March 10, 2013 Author Report Share Posted March 10, 2013 The grass of Maracanã began to be installed http://globoesporte.globo.com/futebol/copa-do-mundo/noticia/2013/03/primeira-parte-da-grama-do-maracana-comeca-ser-instalada.html Link to comment Share on other sites More sharing options...
Bezzi Posted March 10, 2013 Author Report Share Posted March 10, 2013 Link to comment Share on other sites More sharing options...
Athensfan Posted March 10, 2013 Report Share Posted March 10, 2013 No single line about the billion-dollar works to avoid floodings in the Maracana area, to be inaugurated in november. Two underground rivers will get detours and a underground "pool" is under final works to store the flooded waters... Maybe one of the biggest legacies of the World Cup in Rio, but this is not interesting to publish in the Int'l media... Well obviously none of that is working yet. Link to comment Share on other sites More sharing options...
intoronto Posted March 11, 2013 Report Share Posted March 11, 2013 Well obviously none of that is working yet. After all controversy = cash Link to comment Share on other sites More sharing options...
DannyelBrazil Posted March 11, 2013 Report Share Posted March 11, 2013 Well obviously none of that is working yet. Of course, since the detour of the rivers and the "pool" are under works... But, after 50 years of March/April single-day rain floodings in the area, the problem is now addressed. Link to comment Share on other sites More sharing options...