Percentage of construction works so far:

Fortaleza...........71%

Belo Horizonte...62%

Salvador............60%

Brasília..............59%

Rio de Janeiro...54%

Cuiabá...............45%

Recife................43%

Manaus.............40%

São Paulo.........38%

Porto Alegre......30%

Natal.................23%

Curitiba.............20%

UPDATE June-July 2012

HOST CITY | Stadium | Construction progress (%) | Scheduled delivery

BELO HORIZONTE
| Mineirão Stadium |
70%
|
December 2012

BRASÍLIA
| National Stadium |
62%
|
December 2012

CUIABÁ
| Pantanal Arena |
45%
|
December 2012

CURITIBA
| Baixada Arena |
53%
|
June 2013

FORTALEZA
| Castelão Stadium |
78%
|
December 2012

MANAUS
| Amazônia Arena |
41%
|
June 2013

NATAL
| Dunas Arena |
25%
|
December 2013

PORTO ALEGRE
| Beira-Rio Stadium |
30%
|
December 2013

RECIFE
| Pernambuco Arena |
49%
|
February 2013

RIO DE JANEIRO
| Maracanã Stadium |
59%
|
February 2013

SALVADOR
| Fonte Nova Arena |
65%
|
December 2012

SÃO PAULO
| Itaquera Arena |
42%
|
December 2013
Link to comment
Share on other sites

  • 2 weeks later...

Soon i will post the pictures of July. The diference from last month is big. I disagree whit Dannyel. Stadiums is the last thing we have to worry, even Natal or Manaus. These cities won't participate in confederations cup, so no need to hurry.

Link to comment
Share on other sites

Soon i will post the pictures of July. The diference from last month is big. I disagree whit Dannyel. Stadiums is the last thing we have to worry, even Natal or Manaus. These cities won't participate in confederations cup, so no need to hurry.

Let's say I'm a bit worry only, but it's totally achievable to finish the stadium with a enough time for test events.